UK: NESO updates connections reform proposals
NESO and Ofgem confirm additional transitional measures
04 февруари 2025 г.
UK: NESO updates connections reform proposalsNESO and Ofgem confirm additional transitional measures04 февруари 2025 г. Why should I read this?On 15 January 2025, the National Energy System Operator (“NESO”) and Ofgem each published letters on the latest TMO4+ connections reform proposals. In its letter, NESO set out a series of new transitional measures to facilitate the implementation of TMO4+, with Ofgem’s letter approving those measures. Understanding the impact of these measures will be important for anyone seeking a place in the grid connection queue. What are the additional measures?NESO has outlined three additional measures to aid the transition into Connections Reform:
NESO have also confirmed that any agreement variations (ie Agreements to Vary) and notices required to be triggered by the TOs will continue throughout the pause period as ‘business as usual’. Similarly, novations will continue to be processed as they are considered to be immaterial to the G2TWQ process. What else do I need to know about the “pause”?NESO and TOs will use reasonable endeavours to promptly process applications made before the pause period, to enable offers to be issued prior to the implementation of TMO4+. To enable this, by 12th February 2025, NESO will ask that customers have paid their application fee, provided any additional justification requested, and answered any questions from NESO and the relevant TO. If they do not do so by this date, NESO proposes that the application will not be “clock-started”/processed. For demand applications, these must have “clock-started” by 4th April 2025 (two weeks after the application deadline of 21 March 2025). If an application is submitted during the pause period, it will not be accepted and the customer will need to reapply under the TMO4+ process. Customers who make applications and receive offers during this time must ensure that their offers are accepted before the offer acceptance period expires. NESO is proposing to shorten this period (to 4 weeks), which will help offers to be in a signed position by the implementation of TMO4+, so that customers can participate in the G2TWQ process. Failure to accept the offer within the offer acceptance period will result in the offer lapsing. What about DNO connection offers?Distribution network operators (“DNOs”) will not implement a pause period at distribution level. DNOs will continue to provide offers following the receipt of an application. Where there is need to follow the transmission impact assessment process (ie submit a Project Progression to NESO), DNOs have indicated that their preference is to wait until the introduction of the CMP434 window before sending the applications due to NESO. Latest Публикации
Latest News
Latest Събития и обучения
guides and reports 07 октомври 2026 г. How data, AI and digital regulation are reshaping M&A risk legal updates 07 октомври 2026 г. EU: Proposed KIDS Act Targets Online Child Safety guides and reports 07 октомври 2026 г. Technology, AI and the changing legal landscape of M&A guides and reports 07 октомври 2026 г. How AI is democratizing M&A for buyers and investors новини от нас 07 октомври 2026 г. Faster deals, deeper diligence: AI is transforming the legal landscape of M... новини от нас 05 октомври 2026 г. Leading finance partner joins Eversheds Sutherland новини от нас 01 октомври 2026 г. Eversheds Sutherland Switzerland appoints Dr. Michael Faske as new Partner новини от клиенти 21 септември 2026 г. All change: Eversheds Sutherland advises DfT on Chiltern Railways transitio... Събития и обучения virtual Energy Transition Series: Energy Transition and Pricing Volatility 08 октомври 2026 г. 10:00 ET | 15:00 BST | 16:00 CET in-person Labor relations conference - turning legal change into workplace reality 08 октомври 2026 г. 10.00am - 4.00pm (BST) Лондон, Обединено кралство virtual Immigration UK – Right to work and compliance masterclass 15 октомври 2026 г. 9.30am - 12.30pm (GMT) Virtual |