Deconstructing the termination of construction contracts under German Law
A summary of the key considerations encountered when terminating construction contracts under German Law
10 de octubre de 2024
Deconstructing the termination of construction contracts under German LawA summary of the key considerations encountered when terminating construction contracts under German Law10 de octubre de 2024 Overview of the lawThe three key considerations are: The Employer can terminate the construction contract at any time; a justified termination can trigger the Employer’s claims for damages and reimbursement of replacement costs; and a termination without cause can trigger the Contractor’s remuneration claims. What is the German law regarding construction contractsGerman law governs the construction contract as part of the German Civil Code[1] (“Bürgerliches Gesetzbuch” (BGB)). Additionally, the German Construction Contract Procedures (“Vergabe- und Vertragsordnung für Bauleistungen, Teil B” (VOB/B)) contain contractual conditions for the execution of construction work including its termination. The VOB/B are considered as General Terms & Conditions. Construction contracts between companies are usually governed by the VOB/B. Both, the BGB and the VOB/B contain provisions on the termination of constructions contracts. The Employer can terminate the construction contract at any timeThe Employer can terminate a construction contract at any time until completion of the work (so called “free termination” ((Freie Kündigung))[2]. Such termination is possible regardless of whether or not the Contractor has breached any contractual obligation. In case of a “free termination” the Contractor has no right to complete the work but he remains entitled to the agreed remuneration. However, the Contractor must deduct from its remuneration:
The evidence and calculations are usually difficult to provide for the Contractor. Therefore, while the Contractor remains free to calculate the specific amount, the law presumes that the contractor is entitled to 5% of the agreed remuneration for the part of the work not yet performed. Grounds to terminate the contractThe Contractor is not entitled to its remuneration for the work not yet performed at the moment of the reception of the termination if and to the extent that the Employer had grounds to terminate the contract, in particular if the Contractor breached its (contractual) duties. The following circumstances can, depending on the precise circumstances and the type of construction contract, constitute such grounds:
The termination has to be in writing. In the case of termination, the work performed is invoiced according to the contract prices. However, the Employer can claim damages from the Contractor and reimbursement of replacement costs for any unfinished work. Key considerationsAs terminations become more prevalent, greater scrutiny will be placed on contractual provisions around termination and the enforcement of termination provisions. It is essential in both drafting and enforcing termination clauses that formalities and procedures are followed. It is therefore essential that you consider the practical considerations of termination including:
As terminations can occur quickly, we recommend you contact us as early in the process as possible to secure the best outcome in a manner which protects your rights effectively. [1] Sections 631 et seq, specifically in Sections 650a – 650h. [2] see Section 648 of the German Civil Code / Section § 8(1) VOB/B) Últimas Alertas Informativas
Últimas News
Últimas Eventos y formaciones
guides and reports 07 de octubre de 2026 How data, AI and digital regulation are reshaping M&A risk legal updates 07 de octubre de 2026 EU: Proposed KIDS Act Targets Online Child Safety guides and reports 07 de octubre de 2026 Technology, AI and the changing legal landscape of M&A guides and reports 07 de octubre de 2026 How AI is democratizing M&A for buyers and investors noticias de la empresa 07 de octubre de 2026 Faster deals, deeper diligence: AI is transforming the legal landscape of M... noticias de la empresa 05 de octubre de 2026 Leading finance partner joins Eversheds Sutherland noticias de la empresa 01 de octubre de 2026 Eversheds Sutherland Switzerland appoints Dr. Michael Faske as new Partner noticias de clientes 21 de septiembre de 2026 All change: Eversheds Sutherland advises DfT on Chiltern Railways transitio... Eventos y formaciones virtual Energy Transition Series: Energy Transition and Pricing Volatility 08 de octubre de 2026 10:00 ET | 15:00 BST | 16:00 CET in-person Labor relations conference - turning legal change into workplace reality 08 de octubre de 2026 10.00am - 4.00pm (BST) London, Reino Unido virtual Immigration UK – Right to work and compliance masterclass 15 de octubre de 2026 9.30am - 12.30pm (GMT) Virtual |