UK: NESO update timeline for Connections Reform offers
Updated delivery timeline, and locational sequencing confirmed
February 17, 2026
UK: NESO update timeline for Connections Reform offersUpdated delivery timeline, and locational sequencing confirmedFebruary 17, 2026 Connections reform timelineOn Friday 13 February 2026, the National Energy System Operator (“NESO”) issued a joint statement with transmission owners (“TOs”), distribution network operators (“DNOs”) and connection reform delivery partners providing an update on the delivery timeline for Connections Reform. Citing ‘technical and engineering matters’ requiring review as the reason for the updated timeline, NESO has confirmed the following timeframes for offers:
The update from NESO also confirms that offers will be issued on a locational sequencing basis, which means offers will be released on an area by area basis as technical work is completed for a particular area. Customer Support Model introducedThe update also provides NESO and TOs with the opportunity to introduce their centralised customer support model. A multi-organisational support team will be established to provide support to customers receiving Gate 2 offers. The new model will provide customers with a single way to raise technical queries, with defined response times for queries to be answered, as well as clearer guidance as to what can and cannot be changed within an offer. Latest Insights
Latest News
Latest Events
podcasts and webcasts June 11, 2026 PROPcast 2026 - Episode 5 | Upwards-Only Rent Reviews - Latest FAQs on the ... legal updates June 11, 2026 EU adopts renewed foreign investment framework legal updates June 11, 2026 Real Estate of Mind legal updates June 10, 2026 UK: New right to complain to organisations for UK GDPR infringement client news June 09, 2026 Eversheds Sutherland powers 12 key deals for Gresham House Energy Storage F... client news June 04, 2026 Next stop, public ownership: Eversheds Sutherland advises DfT on GTR transi... client news June 04, 2026 Advising Howden Joinery Group plc on ÂŁ390m DIY Kitchens acquisition client news June 03, 2026 A blueprint for growth: Eversheds Sutherland supports Leonard Design Group ... virtual Nordic (Denmark, Finland, Norway and Sweden) employment law training June 16, 2026 12.45pm - 4pm (BST) Virtual virtual Education Webinar - Equality, diversity and inclusion: current developments... June 17, 2026 11:00AM-12:00PM virtual Education Webinar - Capturing IP: securing IP rights in lecture capture and... June 18, 2026 111:00AM - 12:00PM virtual Introduction to Swiss employment law June 23, 2026 2pm - 5pm (GMT) Virtual |